Infosys’ blog on industry solutions, trends, business process transformation and global implementation in Oracle.

« Data Federation – A potent substitute of Data Warehouse? | Main | Demand to Deliver Solution—Remedy for Supply Chain Cost Inflation in Hi-Tech Companies »

Is it possible to achieve "Zero" breakdown in Maintenance World?

In maintenance world when we talk of "Zero Break down" most of the time maintenance crew says that it is not possible to achieve zero break down.  So is it really possible to achieve "Zero Break down" for a Machine /Equipment?  The answer is "Yes". 

What is breakdown? :- When a Machine (M/c)is working and suddenly something fails for e.g. in case of CNC M/c hydraulic hose pipe rupture and it leads to heavy oil leakage, thus Beak down due to hydraulic leakage occurs on the M/C.
Above Failure could have been anticipated by doing regular check of hydraulic hose piping by carrying out proper preventive, predictive maintenance.
What is "Zero Breakdowns"? :- When the Maintenance Department hand over a M/C to Production Department for the Production activities, that time maintenance department can confidently say the M/C would not fail due to "Hydraulic leakage" for another 24 Hrs as they have done a proper inspection/rectification through Preventive and Predictive Maintenance on the M/C  on Hydraulic side. This 24 hrs of running time without any Hydraulic failure is said to be "Zero Break Down" in Hydraulic piping area.
 After 24 Hrs again maintenance team would take the machine in their custody to do preventive and predictive maintenance to ensure that there would not be any failure due to "Hydraulic leakage" for another 24 hrs, thus maintenance team take over the control of M/C after certain running period of the M/Cs and do preventive/Predictive maintenance to achieve "Zero Breakdown" in specific area e.g. 'Hydraulic Pipe failure'. Over a period of time by doing proper, regular preventive maintenance on almost all the areas of M/C instead of specific area leads to achieve Total "Zero Breakdown" on an asset for certain mentioned period time frame by the Maintenance department.

 

What is Preventive and Predictive Maintenance? How Oracle eAM address it?

 

Preventive Maintenance(PM):- A maintenance activity done on a machine at regular interval based on the Preventive Maintenance strategy designed by Maintenance Planning Department by taking inputs from OEM(Original Equipment Manufacturer) recommendation ,Past Maintenance experience and  from  Reliability Centered Maintenance Department,generally at the beginning of each financial year to formulate the Preventive Maintenance execution time frame (PM frequencies) . It does not change frequency of Preventive activities frequently /on ad hoc basis, based on changes and findings during inspection once the PM stagey is defined for the year, which are generally taken care by other type of Maintenance like Predictive Maintenance work.

Case 1
Preventive Activity:- Hydraulic Oil Top up on CNC M/c  once in a month
Why Preventive Maintenance required:- This preventive maintenance  is required to avoid a breakdown due to less oil level which leads to less hydraulic pressures during M/c operation,doing so you can at least achieve Zero Break down due to "Low Hydraulic Oil level", similarly you can indentify frequent failures on M/Cs and try to work on preventive measures  as motioned below
How Oracle eAM Helps to achieve Preventive Maintenance Process:-
In Oracle eAM you can generate Preventive Maintenance Work Orders automatically based on meter readings, runtime and/or calendar days. An example of meter-based preventive maintenance is your vehicle oil changes. Most vehicle manufacturers recommend that you have to change your engine oil every 3,000 miles or six months, whichever comes first. A preventive maintenance definition having combination of meter and calendar days can be defined to achieve engine oil replacement activity based on the manufacturer's recommendation.

 

Predictive Maintenance: - A maintenance activity done on a Machine at regular interval along with Preventive maintenance or on continuous basis inputs from online system e.g. SCADA (supervisory control and data acquisition) or based on the inputs from other sources (e.g. Machine Operator's observation)  .In predictive maintenance the  detailed analysis of the inspection data is done and based on the analysis results prediction of the Failure is determined . To avoid the Failure Machine is taken for the Predictive Maintenance  work which may involve some major overhauling or shutdown .
Case 1
Predictive Maintenance carried out along with regular PM
Predictive Activity:- Oil Inspection & inspection result's detail analysis
Preventive activity: - Hydraulic Oil Top up on CNC M/c one in a month 
Why Predictive Maintenance required: - As a part of normal Preventive Maintenance  activity  oil is topped up every month  in hydraulic power pack, in case of Predictive maintenance oil sample analysis is done in detail e.g. for presence of  metal partials, color of the oil due to contamination etc. Based on the detailed analysis of the oil if it is found that oil is getting contaminated due to small quantity of coolant leakage and it may lead to change in the oil viscosity and ultimately loss of Hydraulic pressure and thus lead to Break down in future. This failure could be avoided by informing Production department to carryout Oil replacement and arresting  of coolant leakage work as predictive maintenance work.
Case 2

Predictive Activity:- Abnormality Observation by a M/C Operator 

Why Predictive Maintenance required: -Other than statistical Method as mention in Case 1,you need a mechanism to record any abnormality observed by operator/cleaner of the machine, as they work on M/Cs on daily basis and knows it's behavior very well and they are first level people who can immediately find  any abnormal behavior in the M/Cs  e.g. suppose the hydraulic hose clamping bolts loosen due to vibration and hosepipe start rubbing against  M/Cs part , this kind of observation could be taken as input to the Predictive maintenance ,M/c could be taken for the tightening of the clamping bolts as Predictive work to avoid the failure due  to sudden rupture of the hose pipe due to rubbing against machine part.

How Oracle eAM Helps to achieve Predictive Maintenance Process :-
Using Oracle eAM and Quality module:-  You can define the collection which would collect the data during Preventive maintenance and in case of deviation in the inspection results system would automatically generate one system generated work order( Predictive work order ).
Using work Request feature:-The inputs from the M/C operators could be recoded as "Predictive work request". Also the Vibration analysis or other external Tools statistical data analysis result can be entered as "Predictive work request "by configuring request type "Predictive" and maintenance manger can approve it for the Predictive work order.

 

Comments

I have few issues related to Oracle eAM module.
Can you help me
Issue related to auto PO generation from job order for service items e.g. Crane Service etc..
thanks
Upadhye Vishwas

Thank you Mr. Vishwas Upadhye for your query , yes it is possible to create a auto PO directly from Oracle eAM Outside processing (OSP) Work Order however it required few configuration steps related to sourcing rule .We already worked on similar requirement during one of our Oracle eAM implementation . Please do let me know if this addresses your query or you would like to discuss this further.

Hi

For predictive maintenance case,if i have any external system which monitors the health of asset by performing inspection on quality parameters and the irregularities reported for an asset gives rise to a work request then how do we integrate this external system to Oracle.Is there any possibility on that to integrate external system to oracle so that out of limit irregular values for quality parameter can be enetered as an automation.

Thank you Mr. Deepankar for your query , external system inputs can be linked to Oracle eAM through interface and based on the inputs Work Request , Work Orders can be generated automatically however this would come under eAM interface development .In case if you are using Oracle Quality module to capture the eAM related inspection irregularities then Standard seeded interfaces are available between eAM and Quality modules which would automatically generate Work Request / Work Orders. Please do let me know if this addresses your query or you would like to discuss it further.

Post a comment

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)

Please key in the two words you see in the box to validate your identity as an authentic user and reduce spam.

Subscribe to this blog's feed

Follow us on

Blogger Profiles